The first phase of this project comprises the
provision of piled foundation with a reinforced ring beam. The
construction up to first floor level on non-habitable garages in
masonry construction off the new foundations to above flood risk
level.
Structural engineers have designed the foundation details and
competitive tenders have been sought and it is proposed to place
the order with the lowest tenderer Gipping Construction.
Enabling works are currently underway with a separate contract and
contractor for the construction of a larger electric sub-station to
supply future developments.