Issue details

On 20 December 2024, Cabinet accepted the Community Regeneration Partnership funding and commenced delivery of the Ten_09 Jaywick Sands Public Open Spaces project. Subsequent Cabinet decisions increased the overall project budget and approved the development of a revised programme of projects.
The original appointment of Adams & Sutherland Ltd was based on a £1.7m construction budget and a programme of eight public open space projects. Since appointment, Cabinet-approved changes to the project budget and scope have significantly increased the scale and complexity of the programme.
The current programme comprises twelve projects, including Brooklands Road, Bay Walk, Enterprise Centre and Dig4Jaywick improvements, vacant plot activation projects and expanded proposals at Crossways Park and St Christophers Green following approval of the revised Ten_09 programme and associated budget increase.
As the project has developed through feasibility, consultation and design stages, substantially more work has been required including additional stakeholder engagement, highways and engineering input, multi-site design development and coordination across a significantly larger programme of projects.
This decision enables completion of the current design stage and provides developed proposals to inform future delivery decisions.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 07/07/2026

Decision due: 7 Jul 2026 by Corporate Director (Place & Wellbeing) & Deputy Chief Executive

Contact: Lee Heley, Corporate Director (Place and Wellbeing) & Deputy Chief Executive Emma Twine Email: etwine@tendringdc.gov.uk Email: lheley@tendringdc.gov.uk.