Issue details
The appointment of the required additional
services are necessary to progress the project through to delivery,
including achieving defrayment in line with the MOU.
- To carry out a Heritage Impact Assessment from Leigh Alston to
support the Scheduled Monument Consent Application
The inclusion of a Heritage Impact Assessment has been specifically
requested by Historic England as part of the Scheduled Monument
Consent application. With our Scheduled Monument Consent approval,
TDC can then apply for our bat licence, and undertake subsequent
mitigation works, before the hibernation season starts in
September, as has been advised by the project ecologist.
The report has been confirmed as a requirement for the Scheduled
Monument Consent application by Historic England as confirmed in
advice received from Adam Single (Inspector of Ancient Monuments
Essex and Herts) in June 2026. Urgent submission of the application
is essential to achieve the above timescales and secure the Bat
Mitigation License, without which would cause a knock-on effect to
the project within the construction phase having both programmatic
and financial implications.
Therefore, this procurement of the additional report is in line
with Section 2 of the Constitution which sub-section 2.1 states: c)
The matter is one of urgency as determined by the appropriate
Corporate Director/Head of Department following consultation with
the responsible Portfolio Holder or the Leader of the
Council.
(e) Where the work is of a specialist nature and the Corporate
Director/Head of Department can demonstrate that it is not possible
to obtain more than one quotation or tender.
Given Leigh’s existing knowledge of the site and the
information already gathered in previous reports, he would be able
to expedite the preparation and completion of the report in line
with our timeframes.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 02/07/2026
Decision due: 2 Jul 2026 by Corporate Director (Place & Wellbeing) & Deputy Chief Executive
Contact: Lee Heley, Corporate Director (Place and Wellbeing) & Deputy Chief Executive Emma Twine Email: etwine@tendringdc.gov.uk Email: lheley@tendringdc.gov.uk.