Issue details

On 6 October 2023 Cabinet considered a report titled ‘Levelling Up Fund and Capital Regeneration Projects - Progressing the Projects to Planning Permission’. As part of that report, Cabinet delegated authority to the Corporate Director Place and Economy in consultation with the Portfolio Holder for Economic Growth, Regeneration and Tourism to procure appropriate resources and commission a project team to carry out the associated work including for the design briefs.
On 9 Oct 2025 a Letter of Claim (LOC) was received from ‘The Property Lawyers’ acting on behalf of leaseholders at Flat 2, 39 Carnarvon Road, Clacton-on-Sea. The LOC asserts a right of light injury from the Development, and requests information in order to assess the full extent of that injury.
Rights of light were considered during the design phase in order to minimise risk of claim however it was not possible to fully design out the risk within the parameters of the deliverables of the Memorandum of Understanding for the funding, as it would have required reduction in the number of housing units created.
This appointment allows the ‘rights of light’ aspect of the design briefs to be progressed further to the above claim, to:
-Consider whether there is a right of light through the relevant window(s);
-Consider whether the proposed development will cause an actionable injury to such right;
-Consider options and next steps for TDC’s position.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 28/10/2025

Decision due: 23 Oct 2025 by Corporate Director (Place & Wellbeing) & Deputy Chief Executive

Contact: Lee Heley, Corporate Director (Place and Wellbeing) & Deputy Chief Executive Email: lheley@tendringdc.gov.uk.

Decisions