As you will be aware, the first floor
changing, shower and toilet areas at Clacton Leisure Centre have
been closed for centre users since February’24, as water
leaks from these areas have caused water ingress and substantial
damage at various ground floor areas including the Wellbeing
Zone.
Further to a leak-detection survey report it has been established
that the existing drainage system needs to be reassessed and
re-designed including floor falls. Further to that, these interior
areas will require an overall make-over. The priority at this stage
is to deliver necessary building condition rectifications to bring
disused spaces back into use in a cost-efficient manner and at
speed, to increase capacity in the short term prior to the
redevelopment coming forwards.
On 19th April 2024 as part of Cabinet meeting – Cabinet
Members' Items - Report of the Portfolio Holder for Corporate
Finance
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 14/03/2025
Decision due: 14 Mar 2025 by Corporate Director (Place & Wellbeing) & Deputy Chief Executive
Contact: Kieran Charles, Sport & Leisure Operations Manager 01255686684, Email: kcharles@tendringdc.gov.uk Email: kcharles@tendringdc.gov.uk.