To agree the final procurement route for the main build contracts and to agree the documentation required to commence procurement for the main build contracts for both Carnarvon Terrace (LUF) and Homes for Dovercourt (CRP)

Decision type: Key

Reason Key: Expenditure or Saving of £100,000 or more;

Decision status: For Determination

Wards affected: Pier;

Notice of proposed decision first published: 17/01/2025

Explanation of anticipated restriction:
Not applicable

Expenditure or Saving: Expenditure;

Decision due: 17 Feb 2025 by Deputy Leader of the Council and Economic Growth, Regeneration & Tourism Portfolio Holder

Lead member: Deputy Leader of the Council and Economic Growth, Regeneration & Tourism Portfolio Holder

Lead director: Corporate Director (Economy and Place) & Deputy Chief Executive

Department: Corporate Business Schedule

Contact: Emma Twine, Project Manager (Levelling Up) Email: etwine@tendringdc.gov.uk.