Issue - decisions
22/07/2026 - CRP2 Ten_11 Martello Tower E - Extend project budget for surveys outlined in the PID
To extend the amount of project budget for
surveys outlined within the Project Initiation Document
(Ten_11-Martello Tower E - PID) from £20,000 to £25,000
as further site surveys are required and we have reached the
initial cap of £20,000.


