24/04/2025 - Clacton Leisure Centre Heating System
a)The Portfolio Holder for Leisure and Public
Realm agrees the strategy set out in this report for addressing the
boiler failure at Clacton Leisure Centre, following an action set
out for delivery in the Council’s Sport and Activity
Strategy;
b)on behalf of the Cabinet and using the special urgency powers, in
accordance with Parts 3.X and 5.8, the Leader of the Council and
Portfolio Holder for Finance and Governance, in consultation with
the Portfolio Holder for Leisure and Public Realm agree for the
Council to accept Salix Funding to the value of £1,204,481
and enter into the Funding Agreement, as set out in Appendix A, for
the purpose of purchasing and installing a new Boiler and
associated plant for Clacton Leisure Centre; and
c) subject to (a) and (b), the Portfolio Holder for Economic
Growth, Tourism and Regeneration together with the Portfolio Holder
for Leisure and Public Realm agree to allocate £164,248 from
the Community Regeneration Partnership Funding, as the
Council’s contribution to the purchase of a new boiler at
Clacton Leisure;
d)subject to (a) and (b) above, that the installation of a new
boiler system for Clacton Leisure Centre is added to the Capital
Programme in 2025/26 with a total budget of £1,368,730.
e)that the Leader of the Council and Portfolio Holder for Finance
and Governance agrees to carry forward £45,000 from the
former Joint Use Sports Centre budget from the 2024/25 financial
year into 2025/26, and allocates this towards a budget which can
fund a temporary oil-fired boiler system for Clacton Leisure Centre
at short notice, as an interim measure, in the event of a failure
of the remaining boiler prior to the project being completed;
f)subject to (d) above, that the Leader of the Council and
Portfolio Holder for Finance and Governance agrees an exemption to
procurement is agreed to allow the Council to appoint its term
contractor, Lindsey Group, to provide the temporary boiler,
associated plant and labour;
g)following (f) it is noted that the Assistant Director Sport,
Leisure and Health will develop the procurement strategy for the
commissioning of the contractors required to deliver the
installation of a new boiler system within the milestones, as
required by the Funding Agreement.
h)It is understood that the decisions above are made in the context
that the Council is bound by the Salix Funding agreement from the
grant start date until 3 years after the project is
completed.