Decision details

Decision Maker: Corporate Director (Operations and Delivery)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The Council has identified voiding beneath the promenade at Harbour Crescent which has resulted in visible movement within the promenade structure. Evidence has also been observed of slight movement within the rear retaining wall.
Specialist works are required to inject expanding polyresin into the voided areas to stabilise the structure and prevent further deterioration. Repointing works to the front face of the wall were undertaken last week, with a facing shuttering added to the wall to assist in containing the injected material, thereby improving the effectiveness of the repair.

Decision:

Investigations have identified voiding beneath the promenade at Harbour Crescent, together with evidence of movement within the promenade structure and the commencement of displacement to the rear wall.
Three quotations were requested with two being received for the required works. Whilst the lower quotation represented better value financially, the contractor was unable to commence works until 10 January. The preferred contractor is able to commence works during the week beginning 16 November, substantially reducing the period during which the asset remains at risk.
Given the existing structural movement, the potential for further deterioration during the winter period and the increased likelihood of severe weather and wave action, it is considered that delaying the works would expose the Council to an unacceptable level of risk. A structural failure could result in significant additional emergency and permanent repair costs, public safety concerns, disruption to the seafront infrastructure and reputational damage to the Council.
On balance, the additional expenditure is considered justified in order to mitigate these risks and secure the earliest practicable completion of the remedial works.

Alternative options considered:

The Council has a duty to manage and maintain its assets in a safe condition. Failure to address known structural defects could expose the Council to potential claims arising from injury, property damage or asset failure.
The urgent nature of the works and the decision to appoint the contractor able to mobilise immediately, means this work should be completed and the risk mitigated well before LGR or Devolution are implemented

Publication date: 09/11/2026

Date of decision: 09/11/2026