Decision details
Decision Maker: Corporate Director (Operations and Delivery)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The Council has identified voiding beneath the
promenade at Harbour Crescent which has resulted in visible
movement within the promenade structure. Evidence has also been
observed of slight movement within the rear retaining wall.
Specialist works are required to inject expanding polyresin into
the voided areas to stabilise the structure and prevent further
deterioration. Repointing works to the front face of the wall were
undertaken last week, with a facing shuttering added to the wall to
assist in containing the injected material, thereby improving the
effectiveness of the repair.
Decision:
Investigations have identified voiding beneath
the promenade at Harbour Crescent, together with evidence of
movement within the promenade structure and the commencement of
displacement to the rear wall.
Three quotations were requested with two being received for the
required works. Whilst the lower quotation represented better value
financially, the contractor was unable to commence works until 10
January. The preferred contractor is able to commence works during
the week beginning 16 November, substantially reducing the period
during which the asset remains at risk.
Given the existing structural movement, the potential for further
deterioration during the winter period and the increased likelihood
of severe weather and wave action, it is considered that delaying
the works would expose the Council to an unacceptable level of
risk. A structural failure could result in significant additional
emergency and permanent repair costs, public safety concerns,
disruption to the seafront infrastructure and reputational damage
to the Council.
On balance, the additional expenditure is considered justified in
order to mitigate these risks and secure the earliest practicable
completion of the remedial works.
Alternative options considered:
The Council has a duty to manage and maintain
its assets in a safe condition. Failure to address known structural
defects could expose the Council to potential claims arising from
injury, property damage or asset failure.
The urgent nature of the works and the decision to appoint the
contractor able to mobilise immediately, means this work should be
completed and the risk mitigated well before LGR or Devolution are
implemented
Publication date: 09/11/2026
Date of decision: 09/11/2026