Decision details
Decision Maker: Corporate Director (Place & Wellbeing) & Deputy Chief Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Background
On 20 December 2024, Cabinet accepted the Community Regeneration
Partnership funding and commenced delivery. Prior to this, the
programme was accepted into the Policy Framework by Full Council on
8 June 2024 and the principle of entering the Partnership approved
by Cabinet on 26 July 2024. Subsequently, the funding has been
received and a Memorandum of Understanding entered with MHCLG which
includes TDC as the Accountable Body.
Reason
The additional fee is based on additional scope requirements,
including in person attendance at 1:1 stakeholder consultation
interviews and additional online and in-person meetings not allowed
for within the original scope.
These additional items were considered requirements to ensure
meaningful engagement not only with local stakeholders but with
Portfolio Holders too.
Value for Money
They have demonstrated value for money of the fee to date, through
the successful delivery of the project to date. They have
undertaken a significant number of additional edits to the Final
Report at no additional cost. Furthermore, this fee is utilising
last year’s rates (making it extremely competitive) and TDC
have already negotiated this fee down with the consultant.
The acceptance of this fee will ensure the project progresses in a
meaningful way, as per the Council’s commitment to date and
as set out in the Project Initiation Document.
Decision:
To approve variation to the contract dated
23rd October 2025 between TDC and Publica Associates Limited
(company number: 7225685). The additional fees are £2,557.91
(cost + 10% contingency, excluding VAT).
These additional fees result from additional scope requirements,
including in person attendance at 1:1 stakeholder consultation
interviews and additional online and in-person meetings not allowed
for within the original scope.
Alternative options considered:
The wider project will include works to
provide improved amenities to residents of and visitors to the
district and deliver improvements to the condition of existing
public realm and open spaces owned by the Council, with a view to
improving condition and managing the ongoing maintenance burden of
such sites.
Publication date: 06/07/2026
Date of decision: 06/07/2026