Decision details
Decision Maker: Leisure and Public Realm Portfolio Holder
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Decision:
(a) To authorise the Assistant Director
(Sport, Culture and Health) to enter into a contract on behalf of
the Council with Re-gen (UK) Construction Ltd to the value of
£433,021.32 from a total budget of £500,000, to
complete the Clacton Leisure Centre Changing Fitness Changing
Refurbishment.
(b) That the balance of the budget which totals £66,978.67 be
allocated to both the contingency for the project and subject to a
procurement process and a further decision, to fund a specialist
consultant to oversee the refurbishment on behalf of the
Council.
Reasons for the decision:
Cabinet considered a report on 17 March 2025
titled
‘COMMUNITY REGENERATION PARTNERSHIP – PROGRAMME UPDATE
AND FURTHER WAVE OF PROJECTS’
The report set out a list of regeneration projects to be agreed
under that scheme in Clacton and Jaywick Sands, together with their
respective governance routes.
The £20m Government funded Community Regeneration Partnership
programme includes a project to refurbish the Fitness Changing
Rooms at Clacton Leisure Centre, under the banner of of
‘Active Wellbeing Centre (Ten_12).’
The ‘Active Wellbeing’ (Ten_12) project was allocated a
budget of £3m in the report and includes the scope and budget
to complete this project.
Delegations in that Cabinet report were agreed for the Portfolio
Holder for Leisure & Public Realm to ‘proceed to agree
the procurement strategy through to award of contract for the
Active Wellbeing Centre Phase 1 project, incorporating urgent
repairs. (Ten_12).
Following this, a further report setting out the detail for each
project was published on 1 August 2025. This agreed the Project
Initiation Document for the Active Wellbeing Centre (Ten_12) and
listed the next milestone as:
‘approve award of main build contract’
A budget of £500,000 was allocated to the urgent repairs
element of the project from the entire budget, to complete the
changing room refurbishment through an executive decision published
on 1 August in the name of Portfolio Holder for Economic Growth,
Regeneration and Tourism.
In order to develop the strategy to procure a main contractor to
complete these works, on 14 March 2025, the Portfolio Holder for
Leisure and Public Realm agreed to the award, appointment and
entering into contract for consultancy works to provide the
resources and capability to oversee these works.
Following completion of a subsequent procurement process for the
main contractor, a winning supplier was identified following a
consensus meeting. As such, this decision will agree to enter into
a contract with the preferred supplier.
The value of the winning tender was £433,021.32, which allows
the balance to be utilised for consultancy (which will be agreed
under a separate decision) and a contingency sum.
Alternative options considered:
(a) Not to proceed with this project –
As this facility is currently out of use, a full service is not
being provided to customers. By agreeing not to proceed with the
project, there would be no funding allocated to proceed in the
future. As this refurbishment is being funded from external
sources, this is an efficient and financially prudent route to
completion.
(b) Not to award the contract – This contractor scored the
highest score following a robust evaluation process. As the
contract price put forward by the supplier was within the estimated
cost for the work, there is no cohesive argument for not making the
award.
Publication date: 22/01/2026
Date of decision: 21/01/2026
Effective from: 30/01/2026
Accompanying Documents:


