Decision details
Decision Maker: Leader of the Council and Corporate Finance & Governance Portfolio Holder
Decision status: Recommendations Approved (subject to call-in)
Is Key decision?: No
Is subject to call in?: Yes
Decision:
(a) that the Corporate Finance & Governance Portfolio Holder on recommendation of Section 151 Officer, approves an exemption under Paragraph 2.2 of the Council’s Procurement Procedure Rules; and
(b) that the Deputy Chief Executive and Corporate Director for Place & Wellbeing, in consultation with the Portfolio Holder for Economic Growth, Regeneration and Tourism, be authorised to award and enter into contract with SRC Group Ltd (of Crown Business Centre, Ardleigh, CO7 7QR, Company number 10850220) for the purposes of undertaking demolition works.
Reasons for the decision:
SRC Ltd. were the sole bidder but were
disqualified for not meeting the SME criteria. As no valid bids
were received, EPP issued Notice UK12: Procurement Termination via
the Find a Tender Service.
Despite this, the bid scored well across all other evaluation
criteria. Officers have assessed the submission, with EPP reviewing
Social Value and Commercial aspects. The external Principal
Designer also confirmed SRC’s compliance and
capability.
Demolition is critical to progressing the project and meeting the
MHCLG funding deadline of March 2027, making it a priority.
Fifteen companies expressed an interest in bidding, but only one
eventually did bid for the works. Since the project has strict
timeframes for funding defrayment, the deliverability of the
project was balanced against requirement to support SMEs via the
CRP programme.
Lessons learnt for the future include:
Having a broader remit for procurement, depending upon scope and
scale of the works required
Encourage SMEs to engage in advance such that we can understand any
capacity or capability gaps.
Alternative options considered:
1. Repeating the ITT, to include non-SMEs: Any
bids received could be deemed compliant, at the cost of substantial
time lost and impact on the overall programme.
2. Not undertaking demolition – this option is not viable for
the delivery of the projects.
Publication date: 10/07/2025
Date of decision: 10/07/2025
Call-in deadline date: 17/07/2025
Current call-in Count: 0
Effective from: 18/07/2025