In March 2024 Burrsville Public Hall suffered significant damage due to a fire started by unconfirmed arson. The insurance claim included management of the reinstatement works. Contractor has been selected in the process of tender managed by the insurance's agent.
The reinstatement works have commenced in December 2024 and completed on 16th May 2025.
The decision is to sign JCT minor works contract appointing Cadman as the contractor for the works.

Decision:

To sign the contract for reinstatement works for Burrsville Public Hall, Great Clacton.

Alternative options considered:

Option 1 - to sign JCT minor works contract
Option 2 -
Option 3 -

Publication date: 25/06/2025

Date of decision: 24/06/2025