Decision details

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

RESOLVED that Cabinet –

 

a)    subject to Full Council agreeing to the allocation of funding, approves the project to stabilise the damaged cliff areas at Holland-on-Sea;

 

b)    subject to a) above, approves the inclusion of the cliff stabilisation scheme within the 2021/22 Capital Programme with a budget of £2.131m, to be funded by utilising £1.5m from the existing beach recharge reserve along with the £631k already set aside for this project;

 

c)    recommends to Full Council that it approves the use of the £1.5m beach recharge reserve to fully fund the proposed cliff stabilisation scheme;

 

d)    instructs officers to seek ways to generate external funding to offset cliff stabilisation costs; and

 

e)    approves on-going representations being made to Government in the light of recent experiences and the continuing, significant and financial challenges faced by the Council in this area.

Report author: Andy White

Publication date: 23/04/2021

Date of decision: 23/04/2021

Decided at meeting: 23/04/2021 - Cabinet