Decision details
Decision Maker: Leader of the Council and Corporate Finance & Governance Portfolio Holder, Leisure and Public Realm Portfolio Holder
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Decision:
In our mutual capacities of Leader of the
Council and Portfolio Holder for Finance and Governance, and
Portfolio Holder for Leisure and Public Realm, we:
a). approve the final Playzone business plans as set out in the
accompanying background report, and authorise the Assistant
Director (Sport, Culture and Health) to enter into JCT agreements
with McArdle Sport to construct Playzone facilities at Clacton
Leisure Centre, Walton on the Naze, Jaywick Sands and
Harwich;
b). agree the schedule of fees and charges, as set out in Table 2
(pricing structure) of the background report; and
c). authorise the Corporate Director (Finance and IT) to include
the associated PlayZone budget amendments in a future Budget
Monitoring Report for Cabinet's consideration.
Reasons for the decision:
At their meeting on 27 June 2025, Cabinet
agreed to install four new “PlayZones” at Clacton on
Sea, Walton on the Naze, Jaywick Sands and Harwich; which are
modern, largely free to use intergenerational multi activity hubs
around the Tendring District, at a total cost of £1,119,257,
with 75% match funding agreed from the Football Foundation
(FF).
Prior to entering into contract for the construction phase, Cabinet
requested that Officers ‘produce business cases for this
scheme with authority for approval and associated actions delegated
jointly to the Leader and Portfolio Holder for Finance and
Governance and Portfolio Holder for Leisure and Public Realm in
consultation with the Corporate Director (Finance and IT),
Assistant Director (Sport, Culture and Health) and Legal
Services.’
Taking the profit and loss information set out in the accompanying
report into account, it is projected that there will be an overall
surplus of £124,727 over the first five years of
operation.
The percentage of anticipated activity across four PlayZone
facilities demonstrates a sustainable financial model, and
activation will continue in advance of construction and once the
facilities are operational.
Alternative options considered:
Not to progress the project any further: Such
a decision would result in the projects being cancelled, and loss
of £839,355 of external funding into the District. As this
project is a key action in providing new free to use facilities in
focussed areas of the District, as set out in the Sport and
Activity Strategy, a key route to delivering a Council objective
would be lost.
To scale down the project and deliver fewer Playzones in the
District: This would reduce the project costs and resourcing
implications involved, but would in turn reduce opportunity and a
platform for increased activity levels across our communities. As
the business planning process suggest there will be no wider
financial implication to the Council it is considered viable to
progress the project through to construction .
Publication date: 14/07/2026
Date of decision: 13/07/2026
Effective from: 22/07/2026
Accompanying Documents: