Decision details

Decision Maker: Corporate Director (Place & Wellbeing) & Deputy Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Remedial works took place to control the levels of legionella on the previous decision,
Decision - Legionella Remedial Works - Dovercourt Bay Lifestyles
It was initially though the tanks would be removed as part of this process, however they were isolated in the short term, and a decision has now been made to remove them as per recommendation from our contractor.

Decision:

A)To enter into an additional purchase order with Concept Environmental Solutions to complete these works which includes removal of additional redundant materials from site since the remedial works took place. The purchase order amount is £3,350.00
B)Portfolio Holder for Finance & Governance and Portfolio Holder for Leisure & Public Realm agree to fund the works from the 25/26 Leisure Capital Projects Reserve. This will mean committing £3,350.00 from this budget.

Alternative options considered:

To stay safe and compliant there are no other options.

Publication date: 02/03/2026

Date of decision: 01/03/2026