Decision details

Decision Maker: Corporate Director (Economy & Place)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Crystal Electronics Ltd was appointed to carry out the necessary work, including the supply, delivery, installation, and certification of the LED installations according to the specification. It was agreed that existing LEDs would not be replaced. Nonetheless, the contractor has kindly identified additional savings through the introduction of 30 x PIRs in key locations where LED panels are already present. The PIRs will promote further savings by switching off lights when no movement is detected in the area.
As such, a decision has been brough forward to amend the current contract with Crystal Electronics Ltd to include these works

Decision:

A) To proceed with the contract variation with Crystal Electronics Ltd to install a further 30 x PIR’s.
B)The total cost for these works is £7,200, excluding VAT. to be funded with £3,200 from the balance of the Sports Reserve account plus £4,000 from the Sport and Leisure Revenue account.

The Portfolio Holder for Leisure and Public Realm has concurred with this decision being made.

Alternative options considered:

Not to install and continue with increased utility costs.

Publication date: 01/10/2024

Date of decision: 01/10/2024