Decision details
Decision Maker: Corporate Director (Operations and Delivery)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
To facilitate the construction of a
replacement access ramp and the replacement of around 25 metres of
the short wall at the northern part of The Naze. The replacement
short wall is part of the continuing fight against coastal erosion
to protect Hamford Water and the surrounding area. Failure to
repair the wall would result in Cormorant Creek being overwhelmed
by the sea, wiping out significant natural habitat and putting at
risk properties and businesses around the Hamford Water area.
The project is tidal dependent, subject to a licence from the
Marine Management Organisation (in the final stages of the
application) and can only be carried out in September/October or
May/June due to wildlife and bird restrictions in the area.
The collaboration agreement will provide grant funding from the
Environment Agency towards the project.
Decision:
To sign and complete the collaboration
agreement with the Environment Agency
Alternative options considered:
Do nothing - around 10 metres of the wall was
lost to the sea over the last winter, if much more is lost the sea
will breach Cormorant Creek and have a significant affect on the
natural habitat and risk to Hamford Water and the properties and
businesses in this area.
Publication date: 15/08/2024
Date of decision: 15/08/2024