Decision Maker: Corporate Director (Economy & Place)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
On 6 October 2023 Cabinet considered a report
titled ‘Levelling Up Fund and Capital Regeneration Projects -
Progressing the Projects to Planning Permission’. As part of
that report, Cabinet delegated authority to the Corporate Director
Place and Economy in consultation with the Portfolio Holder for
Economic Growth, Regeneration and Tourism to procure appropriate
resources and commission a project team to carry out the associated
work including for the design briefs.
This appointment allows the ‘Planning Consultant’ role
within the design team to be awarded.
To enter into a contract with BE FIRST
(REGENERATION) LTD (company registration number 10635656) for the
Carnarvon Terrace project which is being delivered as part of the
wider Clacton Civic Quarter Levelling Up Fund scheme, and for the
Homes in Dovercourt project, which is being delivered as part of
the Dovercourt Town Centre Improvement Corridor scheme.
The services have a total cost of £30,000 (Carnarvon Terrace)
and £16,000 (Homes in Dovercourt) plus VAT.
The services have been procured via the Essex Procurement
Partnership in line with the Tender Rules as set out in the
Tendring District Council constitution.
Option 1 -
Not appointing a consultant. Taking this approach would mean the
works did not progress.
Publication date: 25/04/2024
Date of decision: 24/04/2024