Meeting documents

Reference Number :-2211
Date :-2012/11/07
Decision Maker :-Cabinet
Subject to Call-in :-Yes
Subject of Decision :-Economic Development Strategy and Implementation Plan
Decision :-That

(a) the scope and content of the Specification of Requirements, as attached at A.6 Appendix ‘A’ to the Report of the Regeneration Portfolio Holder, be approved;

(b) the procurement of consultants in line with the Council’s established policies and procedures be approved;

(c) the selection and appointment of consultants against the cost and quality criteria, as attached at A.6 Appendix ‘B’ to the afore-mentioned report, be approved; and

(d) the use of up to £75,000 from the general Regeneration Budget to meet the costs of this commission and any subsequent and/or ancillary costs associated with the project development and delivery, be approved.
Reason for Decision :-Having considered the information submitted and in order to enable this matter to proceed.
Alternative Options Considered :-None
Conflicts of Interest Delared (and Dispensations Granted by the Monitoring Officer) :-None
Contact Officer :-Regeneration Manager – Tom Gardiner
Decision to Take Effect at end of :-2012/11/16
Attachments :-A.6 Report and Appendices Economic Development Strategy (602K/bytes)