Decision Maker: Head of Planning
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Part 3, Schedule 1 - Functions not to be the
responsibility of an Authority's Executive.
The discharge of the Town
A Planning Contravention Notice was issued in
2017 as to breaches of these conditions. Subsequently a certificate
of existing lawful use has been granted under the above reference
to confirm that the conditions concerned have been breached for a
continuous period of over 10 years and thus no further formal
enforcement action can be taken as to the conditions.
No further action needed. Case closed.
Option 1 -
Option 2 -
Option 3 -
Publication date: 10/06/2019
Date of decision: 05/06/2019